The changes reflect the latest stage of the project’s design following consultation, technical studies, engineering assessments and environmental surveys. It does not include land that may be required temporarily for construction or access, or the specific locations of above ground installations (AGIs) – which are still being refined as the design progresses.
In most locations, the project has reduced the corridor consulted on earlier this year from 300 metres to approximately 100 metres. This remains wider than the land expected to be permanently required for the pipeline and provides flexibility for further design refinement as the project progresses.
Further key changes have also been identified:
-
Southwest of Gawsworth and Moss Houses
-
Southeast of Holmes Chapel
-
Southeast of the Dove Holes Quarry to Tunstead AGI
-
South of Abbey Green, near Leek
-
North of Hargrave and Cotton Abbotts
Changes to the project boundary can be viewed on the updated interactive map.
Changes have been developed following the first phase of consultation on the initial project design, which generated more than 5,500 responses from local communities and stakeholders. Together with further technical studies, engineering assessments and environmental surveys, this has helped refine the plans and shape the latest iteration of the project boundary.
Amendments have been made to around 15% of the proposed pipeline route; revising the area of land included within the project boundary while ensuring thepProject’s safe construction and operation.
The updated boundary is being shared for information at this stage. Peak Cluster will consult on these changes in the coming months, providing communities, landowners and stakeholders with an opportunity to learn more about the proposed amendments and share their views.
In November, the project will consult on changes to proposals within Staffordshire, Derbyshire, and Cheshire. In January, it will consult on changes to the proposals associated with the Wirral.
David Parkin, CEO of Peak Cluster Ltd, said, “Since we began developing Peak Cluster, we’ve been following an iterative design process followed by all nationally significant infrastructure projects. Early designs were shared and consulted on to gather feedback which, alongside technical studies, engineering assessments and environmental surveys, has helped us continue to shape the Project, until we apply for development consent from the Government."
“We’ve used this process to understand where our design can be improved and adapted in recognition of public concerns and environmental constraints, while ensuring the Project remains safe, effective and operationally feasible."
“The updated Project boundary demonstrates how we’ve engaged, heard and acted. It shows our commitment to continue working with local communities and stakeholders to develop a Project that takes into account groups’ priorities as far as possible, minimising local impact."
Both consultations will last approximately six weeks and feedback will help inform the next iteration of the project’s design. Specific information on consultation activities, and how the public can get involved, will be shared in October to ensure communities and stakeholders have every opportunity to participate and prepare.
Peak Cluster said its focus for the upcoming consultations is on refining the locations for the pipeline and infrastructure. In addition, there will be further opportunities to provide feedback on other project aspects in the phase 2 consultation in summer 2027. This will include more detail on the overall project design, construction and operation.